Plaqumine High School getting state-of-the-art athletic upgrades

Plaqumine High School Getting State-Of-The-Aart Athletic Upgrades

Iberville Parish School Board selected Manchac Consulting Group for the design of their new artificial turf football field and relocation of the field events in the D zones of the field.  The geotechnical investigation indicated soil conditions that would allow for the use of soil cement as a base course rather than limestone, saving the School Board just over $100k. Manchac completed the design in 30 days and the construction contract allowed for 80 calendar days for completion. The contractor has worked seven days a week and is currently ahead of schedule and will have the field ready for the first game of the season in late August. Construction contract was $985k which included bleacher modifications also.